Case Study

Octavius saves 6 months on Geotechnical scheme planning

Download PDF
Arrow right
Above
Octavius teams measuring the height profiles of the embankment slippage from their desktop using a topographical survey in Sensat.

Case study overview

"We halved the time it normally takes to hand plans back to the client for approval—what took us 6 weeks using Sensat typically has taken 3 months to complete."

Sean Coleman Innovation & Quality Manager at Octavius Infrastructure.

Challenges faced

An embankment slippage, caused by the natural movement of earth, risked infringing on the UK’s busiest orbital motorway. To correct the issue, Octavius was given a standard unfinished design by the contractor. The team needed to complete these designs and make a swift start to the programme works due to the imminent bird nesting season. Which limited the timeframe to cut down vegetation. Missing this window would cause several months of delay.

Learn how Octavius is using Sensat for:

  • Accurate earthworks measurement
  • Minimised night shifts and disruption
  • Faster stakeholder approvals
  • Identifying traffic management sharing opportunities